| S.No | Project Tiltle | Name of Client | Service Discription | Start Date | Completion Date |
| 1. | Suspension Bridge for Achham District | DOLIDAR | Survey Design and Cost Estimate Preparation | June. 2001 | Jul-01 |
| 2. | Dolakha Lamabagr road (62Km) for Upper Tamakoshi Hydroelectric Project | Nepal Electricity Authority | Detailed Engineering Survey and Design | Dec-01 | Jul-03 |
| 3. | 7 nos. of bridges on Dolakha Lamabagar road for Upper Tamakoshi Hydroelectric Project | Nepal Electricity Authority | Detailed Engineering Survey and Design | May-03 | May-03 |
| 4. | Mude-Doramba-Manthali Road, Raramba | District Road Office, Ramechap | Detailed Survey, Investigation, Design and Report Production | Jan. 1995 | Jun-95 |
| 5. | Tadi Khola Suspension Bridge | District Development Committee, Nuwakot | Survey Design and cost Estimate preparation | Jan. 1995 | Jun-95 |
| 6. | Tinthana Kritipur Miteri Pul, Kalanki | Users Committee tinthana-Kirtipur Miteri Pul. Kalanki | Investigation, Detail design and Construction Supervision | Feb. 1997 | May-97 |
| 7. | Khenchet-Deurali Road Project, Nuwakot | District Development Committee, Nuwakot | Detailed Survey, Investigation, Design and Report Production | March-89 | Jun-90 |
| 8. | Access Road to Tibetan Trekking camp | United Nations High Commissioner for Refugees, Kathmandu | Detail survey, design, Quantity and Cost Estimate | June. 1998 | Sept. 1998 |
| 9. | Lalbandi-Hospital Road, Lalbandi | Seva Foundation, USA | Detailed Survey, Investigation, Design and Report Production | Aug. 1990 | Dec. 1990 |
| 10. | Feasibility Study, Detailed Engineering Survey, Soil Investigation & Detailed Design of Bridge over Judia Khola at Biratnagar- Thalaha, Morang |
Ministry of Physical Planning and Works Department of Roads |
Feasibility Study, Detailed Engineering Survey, Soil Investigation & Detailed Design of Bridge | July-90 | March 2009 |
| 11. | Feasibility Study, Detailed Engineering Survey, Soil Investigation & Detailed Design of Bridge over Singiya Khola at Biratnagar 11-18,Vhatigunj, Morang |
Ministry of Physical Planning and Works Department of Roads |
Feasibility Study, Detailed Engineering Survey, Soil Investigation & Detailed Design of Bridge | July-90 | March 2009 |
| 12. |
Feasibility Study, Detailed Engineering Survey, Soil Investigation, Hydrological Study, Cost and Quality Estimate of RCC Bridges namely:
|
Ministry of Physical Planning and Works Department of Roads, Design and Planning Section Bridge Unit |
Detailed Feasibility Study and Report Production | 2009 | |
| 13. |
Detail Engineering Survey and Design of Bridges along Dolakha-Lamabagar Access Road Project of the Upper Tamakoshi Hydroelectric Project namely:
|
Soil, Rock and concrete Laboratory (SRCL | Detailed Feasibility Study and Report Production | February 2004 |