| S.No | Project Tiltle | Name of Client | Service Discription | Start Date | Completion Date |
| 1. | Nuwakot District rural Electrification Project |
CIMMCO International, Delhi |
Detailed Survey, Investigation and Data Collection | Aug. 1986 | Dec. 1986 |
| 2. | Charnawati Hydropower project (1MW |
Gayatri Hydropower Development |
Feasibility Study | March-02 | Sep-03 |
| 3. | Q/A/a/c work of Kailali – kanchanpur Rural electricity project (KKREP) | INTERTEC-ALSTROM | Grid extension of 11Kv lines for existing Sub Station and Q/A/a/c work | Jun 2003 | Dec 2003 |
| 4. | Kailali Kanchanpur Rural Electrification Project (KKREP) | NEA | Formation of Load Center Based Electricity Users Cooperative in Kailali and Kanchanpur Districts. | Feb-05 | July, 2007 |
| 5. | Power System Management in Nepal | Water and Energy Commission, Secretariat | A Study of Power System Management in Nepal | June, 2007 | July, 2007 |
| 6. | GPS survey system I in Kailali Kanchanpur districts rural electrification project | ESAP | GPS survey of poles, transformer, stay lines, house | 2004 |
2007 |
| 7. | Gumu Khola hydropower Project (1MW) |
Self Development |
Feasibility Study | August-03 | Feb, 2009 |
| 8. | Dolti khola Hydropower Project (1MW) |
Self Development |
Feasibility Study | October-03 | 2009 |
| 9. | Poldumki Hydropower Project (1MW) | Details Geotechnical Study of project area and civil construction sites | May 2009 | June 2009 | |
| 10. | Hetauda Dhalkebar 400 KV transmission line corridor project | NEA | Detailed Survey | Jan 2010 | June 2010 |
| 11. | Power Evacuation study of Tamor Hydroelectric Project 380 MW capacity | Nepal Electricity Authority | Evacuation Study | April 2010 | June 2010 |